Marine

MRV Alba na Mara: survey 0515A programme

July 7, 2015 by No Comments | Category Compliance, Marine Directorate general, Marine Directorate Science, Research Vessel Surveys

Duration: 18-25 April 2015

Gear: Surface and subsurface PAM moorings

Objectives:
To deploy a series of moorings comprising either dhan buoys (maximum of ten surface) or acoustic release systems (minimum of 20 subsurface) and recording devices (30 CPOD and ten SM2M) as part of the east coast marine mammal monitoring programme (see Table 1 and Figure 1).

Procedure:
Loading of all equipment will be carried out on 17 April then Alba na Mara will sail from Fraserburgh on the morning of 18 April and make for the first mooring position.  The ultimate order in which the moorings are deployed will be dictated by the current weather forecast and the likely shelter that can be provided by the east coast.  Accurate position records will be kept detailing where the moorings are eventually placed as this may differ from the planned position. Once all the moorings have been deployed Alba na Mara will return to Fraserburgh by 25 April to unload any remaining gear and disembark the scientific crew.

*******************************************************

Table 1: ID, name and geographic position of all 30 moorings to be deployed in April 2105. Potential surface positions highlighted in grey.

Table 1: ID, name and geographic position of all 30 moorings to be deployed in April 2105. Potential surface positions highlighted in grey.

*******************************************************

Figure 1: Positions of all 30 moorings to be deployed during cruise 0515A.

Figure 1: Positions of all 30 moorings to be deployed during cruise 0515A


Comments

Leave a comment

By submitting a comment, you understand it may be published on this public website. Please read our privacy policy to see how the Scottish Government handles your information.

Your email address will not be published. Required fields are marked *